[DOC] workflows: added remaining sections for the Activities.
bzr revid: vmt@openerp.com-20130724152518-gab0fa44t8a81u30
This commit is contained in:
parent
eff32c650c
commit
33ab08b8b3
|
@ -151,6 +151,14 @@ be chosen on a per-transition basis with the ``trigger_expression`` attribute.
|
||||||
.. note:: Note that triggers are not re-installed whenever the transition is
|
.. note:: Note that triggers are not re-installed whenever the transition is
|
||||||
re-tried.
|
re-tried.
|
||||||
|
|
||||||
|
Splitting and joining transitions
|
||||||
|
'''''''''''''''''''''''''''''''''
|
||||||
|
|
||||||
|
When multiple transitions leave the same activity, or lead to the same
|
||||||
|
activity, OpenERP provides some control about which transitions will be
|
||||||
|
crossed, or how the reached activity will be processed. The ``split_mode`` and
|
||||||
|
``join_mode`` attributes on the activity are used for such control.
|
||||||
|
|
||||||
Activities
|
Activities
|
||||||
----------
|
----------
|
||||||
|
|
||||||
|
@ -207,3 +215,64 @@ activities normally and send to the parent workflow instance a signal with
|
||||||
|
|
||||||
In other words, it is possible to react and take transitions in the parent
|
In other words, it is possible to react and take transitions in the parent
|
||||||
workflow as activities are executed in the sublow.
|
workflow as activities are executed in the sublow.
|
||||||
|
|
||||||
|
Server actions
|
||||||
|
''''''''''''''
|
||||||
|
|
||||||
|
An activity can run a "Server Action" by specifying its ID in the ``action_id``
|
||||||
|
attribute.
|
||||||
|
|
||||||
|
Python action
|
||||||
|
'''''''''''''
|
||||||
|
|
||||||
|
An activity can run some Python code, provided through the ``action``
|
||||||
|
attribute. See the section about transition conditions to read about the
|
||||||
|
evaluation environment.
|
||||||
|
|
||||||
|
Split mode
|
||||||
|
''''''''''
|
||||||
|
|
||||||
|
After an activity has been processed, its outgoing transitions will be tried.
|
||||||
|
Normally, if a transition can be taken, OpenERP will do it and proceed to the
|
||||||
|
activity the transition leads to.
|
||||||
|
|
||||||
|
Actually, when more than a single transition is leaving an activity, OpenERP
|
||||||
|
can proceed, or not, depending on the other transitions. That is, the condition
|
||||||
|
on the transitions can be combined together, and the combined result will
|
||||||
|
instruct OpenERP to cross zero, one, or all the transitions. The way they are
|
||||||
|
combined is controlled by the ``split_mode`` attribute.
|
||||||
|
|
||||||
|
There are indeed three modes to decide how to combine the transition
|
||||||
|
conditions, ``XOR``, ``OR``, and ``AND``.
|
||||||
|
|
||||||
|
``XOR``
|
||||||
|
When the transitions are combined with a ``XOR`` split mode, as soon as a
|
||||||
|
transition with a condition that evaluates to true is found, the
|
||||||
|
transition is taken and the other will not be tried.
|
||||||
|
|
||||||
|
``OR``
|
||||||
|
With an ``OR`` mode, all the transitions with a condition that evaluates to
|
||||||
|
true are taken. The remaining transitions will not be tried later.
|
||||||
|
|
||||||
|
``AND``
|
||||||
|
With an ``AND`` mode, OpenERP will wait for all transition conditions to
|
||||||
|
evaluate to true, then cross all the transitions at the same time.
|
||||||
|
|
||||||
|
Join mode
|
||||||
|
'''''''''
|
||||||
|
|
||||||
|
Just as departing transition conditions can be combined together to decide
|
||||||
|
whether they can be taken or not, arriving transitions can be combined together
|
||||||
|
to decide if an activity must be run. The attribute to control that behavior is
|
||||||
|
called ``join_mode``.
|
||||||
|
|
||||||
|
The join mode is a bit simpler than the split mode: only two modes are
|
||||||
|
provided, ``XOR`` and ``AND``.
|
||||||
|
|
||||||
|
``XOR``
|
||||||
|
An activity with a ``XOR`` join mode will be run as soon as a transition is
|
||||||
|
crossed to arrive at the activity.
|
||||||
|
|
||||||
|
``AND``
|
||||||
|
With an ``AND`` mode, the activity will wait for all its incoming
|
||||||
|
transitions to be crossed before being run.
|
||||||
|
|